Project Scope:
   To design a CSO Green solutions Demonstration Project. The Green Solutions Demonstration Project when complete will consist of a basin located south of NE Parkway and east of NW parkway. The basin will capture and detain storm water until the downstream combined sewer overflow has subsided. At which point it will release the water which will then flow to the treatment plant instead of bypassing to the Missouri River.  

Project Funding:
   2007 Sewer Bonds
   2015 A IDA Bonds
   CIP Sales Tax
   MISC
   SEWER FUND
   SEWER FUND BAL

Project Funding Amount: $429,666.77

Update:
   CSO Green Demonstration Project: This summer, the controls system will be augmented to improve performance and additional plantings will be added to the wetland. 