Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Urban Trail Signage
 

Project Information

Urban Trail Signage
308-215

Project Manager: Rick Spriggs

Current Project Status: Construction

Project Scope:
   To Place signage throughout the Urban Trails. with mile markers and other signage 

Project Funding:
   CIP Sales Tax
   Donation
   MPO/STP-Funds

Project Funding Amount: $46,304.54

Update:
   Work continues as weather allows on the placement of the trail markers. Percent complete is about 95%. 

Last Update: Monday February 27, 2017