Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Blacksnake Creek Stormwater Separation Project
 

Project Information

Blacksnake Creek Stormwater Separation Project
513-010

Project Manager: David Frazier

Assistant Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
    

Project Funding:
   2015 A IDA Bonds
   2016 SRF Funding
   2017 SRF Funding
   Over-payment from Property Closings
   Recovery Reimbursement
   SEWER FUND BAL

Project Funding Amount: $59,496,542.45

Update:
   Blacksnake Combined Sewer Rehabilitation Crack Repair: Utility Solutions mobilized in late June and have working between the Inlet Structure and MH 67-80 or completing approximately 6500-ft. Blacksnake Creek Stormwater Separation Improvement Project Tunnel Package: Super Excavators have prepared the staging pad area, brought in the Job Trailers and enclosed the compound with fencing between the RR tracks and MacArthur Drive. They have also started the sheet pile shoring for the outfall structure on Roy’s Branch Creek. Blacksnake Creek Stormwater Separation Improvement Project Conveyance Package: A Conditional Notice to Proceed was issued to September 5, 2017. The playground equipment has been installed and Mega is currently waiting for the rubberized pavement to be placed under the equipment. Mega has mobilized in some of the concrete boxes to begin laying on October 2nd.  

Last Update: Thursday September 28, 2017