Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Blacksnake Creek StormWater Separation Project
 

Project Information

Blacksnake Creek StormWater Separation Project
513-010

Project Manager: David Frazier

Assistant Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
    The Blacksnake Combined Sewer Rehabilitation Crack Repair package generally consists of repair of concrete and brick cracks in the Blacksnake Combined Sewer pipeline, removal of encrustation and deposits at select lateral connection locations, surface repair of plugged lateral connections and repair of existing missing brick locations. The Blacksnake Creek Stormwater Separation Project Tunnel Package generally consists of the construction of 90-inch diameter concrete precast segment lined 6,648-foot long tunnel, 37-foot diameter baffle drop shaft, 48 feet of near surface reinforced concrete box culvert, 2-foot diameter vent shaft, l8l feet of 90-inch diameter open cut steel pipe installation, l25 feet of 90-inch jacked steel pipe, an energy dissipation structure and site restoration. The Blacksnake Creek Stormwater Separation Improvement Conveyance Package generally consists of the construction of a 7-feet by 6-feet below-grade precast box culvert 5,729 feet in length with four junction structures and an inlet structure, construction of an inlet structure to the existing Blacksnake Combined Sewer System, rehabilitation of a screening structure and slide gate within the existing Blacksnake Combined Sewer System, improvements to approximately 900 linear feet of the existing Roy’s Branch channel near the Missouri River and site restoration.  

Project Funding:
   2015 A IDA Bonds
   2016 SRF Funding
   2017 SRF Funding
   Over-payment from Property Closings
   Recovery Reimbursement
   SEWER FUND BAL

Project Funding Amount: $59,496,542.45

Update:
   Blacksnake Combined Sewer Rehabilitation Crack Repair: Utility Solutions is performing final completion video of Blacksnake sewer conduit and preparing for project closeout. Blacksnake Creek Stormwater Separation Improvement Project Tunnel Package: Super Excavators are continuing to working on the receiving shaft near Second Harvest which is approximately 90% complete. The entrance shaft and staging area is complete and is being stockpiled with miscellaneous tunnel equipment. The subcontractor Foley has completed the main outfall structure and is working on the outfall apron. The Tunnel Boring Machine (TBM) arrived in Seattle in May 26 with a tentative arrival date of June 6 to the project site. Blacksnake Creek Stormwater Separation Improvement Project Conveyance Package: Mega is tying in the box culver sections to bypass structure. Mega set the new prefabricated bridge and has finished the channel around the Remington Center and has restored the trail along River Front Park. Mega is in the process of backfilling the Sewer Intercept Structure and should complete the structure by the first of June.  

Last Update: Tuesday May 29, 2018