Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
New Fire Station (Station 9)
 

Project Information

New Fire Station (Station 9)
313-200

Project Manager: Larry Whittington

Assistant Project Manager: Mike  Dalsing

Current Project Status: Design

Project Scope:
   To Build 2 New Fire Stations: Use Station 12 savings and Geiger Mansion proceeds to acquire land for three stations. This station will be called #9 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $899,324.36

Update:
   Design is nearing completion with a meeting scheduled for March 2nd to review 95% complete documents. After review bid is anticipated for mid March. 

Last Update: Wednesday March 1, 2017