Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
New Fire Station (Station 9)
 

Project Information

New Fire Station (Station 9)
313-200

Project Manager: David Frazier

Assistant Project Manager: Mike  Dalsing

Current Project Status: Construction

Project Scope:
   To Build 2 New Fire Stations: Use Station 12 savings and Geiger Mansion proceeds to acquire land for three stations. This station will be called #9 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $899,324.36

Update:
   The contract for construction was awarded to E.L. Crawford Const. Company, and work is underway at the site. The site has been graded to subgrade level. Footings are installed, under-slab plumbing should be completed this week and the under-slab electrical work is just starting. 

Last Update: Wednesday August 2, 2017