Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Karnes Road/Parkway Realignment
 

Project Information

Karnes Road/Parkway Realignment
313-015

Project Manager: David Frazier

Assistant Project Manager: Andy Clements

Current Project Status: Design

Project Scope:
   Realign Karnes through North West Parkway to eliminate intersecting at St. Joseph Avenue and Extending Cook Road from St. Joseph Aveenue to Savannah Road. This also uses 2008 CIP 2.4 million  

Project Funding:
   CIP Sales Tax

Project Funding Amount: $3,000,000.00

Update:
   Design is ongoing, and the estimated project cost is being prepared. The goal is to bid this work in early April of 2017. 

Last Update: Thursday March 30, 2017