Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Cook Road Extension
 

Project Information

Cook Road Extension
313-020

Project Manager: Brady McKinley

Assistant Project Manager: Roger Sparks

Current Project Status: Design

Project Scope:
   Extending Cook Road from St. Joseph Aveenue to Savannah Road. This uses 2008 CIP 2.4 million  

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,400,000.00

Update:
   The Cook Road Extension project opened bids on March 9, 2017 and City Council will vote to award the contract for construction on March 27, 2017. Construction will begin in late April 2017 with substantial completion occurring on August 18, 2017 and final completion on September 1, 2017. 

Last Update: Thursday March 23, 2017