Cook Road Extension
 

Project Information

Cook Road Extension
313-020

Project Manager: Brady McKinley

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Extending Cook Road from St. Joseph Aveenue to Savannah Road. This uses 2008 CIP 2.4 million  

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,400,000.00

Update:
   The sanitary sewer installation is complete and the contractor will begin construction of the box culvert the first week in August. This project was originally scheduled to be complete by September 1, 2017 and due to unforeseeable delays caused by high water tables the completion date has been moved to November 1, 2017. Savannah Road connection to Saint Joseph Avenue has been closed and will remain closed for the duration of the project until the new Cook Road connection to Saint Joseph Avenue is complete Detours have been signed via Miller Road to Blackwell and Karnes Roads and have been performing well. This project, when completed, will provide a new three lane roadway section across Blacksnake Creek directly connecting Cook Road to Saint Joseph Avenue. Turn lanes will be provided on Cook Road and Saint Joseph Avenue to relieve traffic congestion at the intersection.  

Last Update: Thursday July 27, 2017