Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Mansfield Road
 

Project Information

Mansfield Road
313-035

Project Manager: Brady McKinley

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Mansfield Road from 9th to 22nd. Street Flatten, Widen to 12 ft lanes, improve drainage and add sidewalks. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,000,000.00

Update:
   Construction of this project is well underway with over 75% of the roadway work completed to date. Utility relocations slowed the contractor but they are approximately 3 weeks behind of schedule for completion. All major earth moving and the new enclosed storm water system has been completed. Curb and Gutter on 80% of the project has been installed along with roadway base rock and 70% of the connecting concrete driveways. The contractor expects to have the base asphalt placed on 80% of the roadway by early August, weather providing. The contractor is on schedule to have substantial completion achieved by September 1, 2017 with final completion in late September.  

Last Update: Thursday July 27, 2017