2015 Contracted Mainline Sewer Repairs
 

Project Information

2015 Contracted Mainline Sewer Repairs
513-030

Project Manager: Keven Schneider

Assistant Project Manager: Andy Clements

Current Project Status: Construction

Project Scope:
   Mainline Contracted Sewer Repairs throughout the City. 

Project Funding:
   SEWER FUND

Project Funding Amount: $1,850,442.00

Update:
   Fiscal Year 2015 Account 6430-1730 Data Total Approved Budget $1,874,300.00 Sum of Paid $889,969.80 Balance after Payments $864,877.09 Active $771,547.53 Sum of Balance after Active $93,329.56 Sum of PO Requested $27,500.00 Sum of Left to Use $65,829.56  

Last Update: Friday October 21, 2016