Rosecrans Lagoon Liner
 

Project Information

Rosecrans Lagoon Liner
513-080

Project Manager: Lee Sommers

Current Project Status: Design

Project Scope:
   For Burns & McDonnell Engineering Company for the conceptual design modifications to the Rosecrans Lagoon Liner. 

Project Funding:
   2015 A IDA Bonds

Project Funding Amount: $1,000,000.00

Update:
   Burns and McDonnell are working on developing the 30% design of the Package WWTP. BM has requested that the WPC operational staff take some additional influent samples and perform additional testing that indicated that the previous samples were an anomaly. BM are ready to start finalize their recommendations for final design.  

Last Update: Thursday July 27, 2017