Urban Trail Phase 20, Riverside Extension Part 2
 

Project Information

Urban Trail Phase 20, Riverside Extension Part 2
313-120

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Design

Project Scope:
   To construct an Urban Trail extension on Riverside Road from Faraon Street to Messanie Street. Calling this Riverside Phase 2 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds

Project Funding Amount: $170,000.00

Update:
   MoDOT has now made comments for this project. The plans have now been updated with their comments and now back in MoDOT’s hands for their approval.  