Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2015 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2015 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Bidding and Award

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds
   Transportation Alternative Program (TAP)

Project Funding Amount: $427,922.00

Update:
   MoDOT has approved the supplemental agreement for this project. The city council has now approved the contract with TNR Construction and the books are in the contractor's hands to be signed. 

Last Update: Thursday August 23, 2018