Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2015 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2015 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Land Acquisition

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $855.00

Update:
   MoDOT has now giving us an "A" date to state talking to the property owners on getting the permanent and temporary easements needed to do the project. MoDOT also informed us that a review appraisal will be needed for the appraisals that were done. A PO has been cut for the review appraiser to do the work.  

Last Update: Wednesday April 26, 2017