Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2015 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2015 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds
   Transportation Alternative Program (TAP)

Project Funding Amount: $427,922.00

Update:
   No new progress has been made on the project due to cold winter weather. During these winter months’ time is not counted as per MoDOT’s rules. The contractor will work on the project as the weather allows. 

Last Update: Tuesday February 26, 2019