2018 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2018 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Land Acquisition

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $855.00

Update:
   The appraiser has finished the appraisals for all 5 properties for this project. All the information has now been sent to MoDOT so we can get an “A” Date for this project. Once we get an “A” we can then proceed with talking to the property owners about getting the Permanent and temporary easements for this project. 

Last Update: Monday March 13, 2017