Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Rehabilitate Taxiway/Taxilane
 

Project Information

Rehabilitate Taxiway/Taxilane
413-060

Project Manager: Abe Forney

Assistant Project Manager: Roxanne Patton

Current Project Status: Post-Construction

Project Scope:
   Furnishing professional, technical, and other personnel and the equipment, material and all other necessities to accomplish the development of a concrete taxilane and apron located east of the existing apron and a new surface parking lot. Project will consist of approximately 4,700  

Project Funding:
   Airport CIP
   MODOT BLOCK GRANT

Project Funding Amount: $67,682.00

Update:
   Furnishing professional, technical, and other personnel and the equipment, material and all other necessities to accomplish the development of a concrete taxilane and apron located east of the existing apron and a new surface parking lot. Project will consist of approximately 4,700 square yards of concrete paving and include surface drainage, storm drainage, under-drains, seeding and markings. An Independent Fee Estimate by Rood and Associates has been completed. Midland Surveying completed survey areas for new surfaces per Jviation contract. This project has been concluded. The design for this project requires no further action. Remaining funds are to be released and project closed. 

Last Update: Thursday March 23, 2017