Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2016 Contracted Mainline Sewer Repairs
 

Project Information

2016 Contracted Mainline Sewer Repairs
513-040

Project Manager: Keven Schneider

Assistant Project Manager: Andy Clements

Current Project Status: Construction

Project Scope:
   Mainline Contracted Sewer Repairs throughout the City. 

Project Funding:
   SEWER FUND BAL

Project Funding Amount: $1,946,200.00

Update:
   Date 6/22/2016 Fiscal Year 2016 Account 6430-1730 Values Total Sum of Approved Budget $1,926,200.00 Sum of Final Costs $936,479.03 Sum of Bal after paid $989,720.97 Sum of Active $686,465.86 Sum of Bal after Active $303,255.11  

Last Update: Wednesday August 31, 2016