9th and Felix Street Parking Garage
 

Project Information

9th and Felix Street Parking Garage
313-425

Project Manager: Lee Sommers

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   The city and Mosaic Life Care are working together on a plan to replace the parking garage, located at 9th & Felix Street. Mosaic has begun the preliminary design of the structure. The parking garage is located in a flood plain and floodway and in order to make improvements to the structure, a hydraulic study needs to be completed to amend the flood maps 

Project Funding:
   CIP Sales Tax
   Parking Fund Source ( 1230 )

Project Funding Amount: $1,500,000.00

Update:
   Kissick has completed the box culvert run down 9th St. and completed the tie-in to the inlet structure. Do to the delays by ATT Kissick is proceed with the north box culvert run along Felix St. by casting in place 21-ft of box culvert in order to get by the live ATT duct bank. The remainder of the precast section have been placed along with the 24-in Sanitary Sewer tie-in to the 8th and Felix Manhole. The City has is working with Kissick to resolve CO 1. ATT’s subcontractor H&K continues is assisting ATT splicing crews in rerouting the phone and fiber optic lines.  

Last Update: Wednesday February 22, 2017