Urban Trail Patee Branch Phase 2 from 20th Street to Mitchell Ave.
 

Project Information

Urban Trail Patee Branch Phase 2 from 20th Street to Mitchell Ave.
313-145

Project Manager: Rick Spriggs

Current Project Status: Land Acquisition

Project Scope:
   To build a trail from 20th Street to 28th Street 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $4,625.00

Update:
   The City of St. Joseph is now in the process of getting the paperwork to the council for approval to applied for the grant on this project.  