Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Taxilane Reconstruction ( barrel hanger, rehab and apron,)
 

Project Information

Taxilane Reconstruction ( barrel hanger, rehab and apron,)
413-160

Project Manager: Roxanne Patton

Assistant Project Manager: Abe Forney

Current Project Status: Design

Project Scope:
   Taxilane reconstruction (barrel hanger, rhab. and apron) 

Project Funding:
   Airport CIP
   FAA GRANT
   MODOT BLOCK GRANT

Project Funding Amount: $1,762,546.32

Update:
   T-Hangar Taxilane Project Only: Construction Notice to Proceed March 20, 2017 for a 75-day contract. Ordinance authorized a contract with Ideker for pavement replacement of the T-hangar taxilanes in the amount of $1.329,776.00. Project is on schedule. Fly ash will be placed the week of April 24th, with concrete placed in two weeks. The project has been extended to be 88 calendar days from the original 75 due to some unsuitable soil and buried concrete. The fly-ash has been tilled into the soil and the subgrade rolled. Base rock is about 80% complete. Apron and Barrel Hangar DESIGN: Pre-bid conference scheduled June 6, 2017 at 11:00 am at Rosecrans Airport. T- Hangar Taxilane Reconstruction: Design is complete. Construction Management phase remaining amount is $39,035. Apron and Barrel Hangar Rehabilitation: Waiting on signed design agreement. Construction management and project construction funding pending MoDOT approval and award notification. T-Hangar Taxilane Project: Contractor Change Order #2 approved by City and MoDOT for additional reinforced concrete pipe, and conduit, in the amount of $17,802.00. Construction complete. Final project walk-through complete with no issues. Apron and Barrel Hangar Design: Waiting for consultant design (Fall 2017).  

Last Update: Friday July 21, 2017