Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
New Fire Station ( Station 11)
 

Project Information

New Fire Station ( Station 11)
313-205

Project Manager: Larry Whittington

Assistant Project Manager: Roger Sparks

Current Project Status: Design

Project Scope:
   To build a new Fire Station at 2016 to 2020 South 22nd Street 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $297,500.00

Update:
   Bids were received with Crawford Construction being the low bidder. Contract was awarded to Crawford Construction. Pre-construction meeting is scheduled with all parties involved on June 6th at Firestation HQ. Final plat mylars for Phoenix Subdivision are being circulated within City Hall for signatures and will be filed as soon as possible. Ground breaking is anticipated for late June or early July. 

Last Update: Thursday June 1, 2017