Mobile Data Computer (MDC) Conversion Project
 

Project Information

Mobile Data Computer (MDC) Conversion Project
460-315

Project Manager: Mary Gaston

Assistant Project Manager: Andy Clements

Current Project Status: On-Going

Project Scope:
   Upgrade the substantially out of date mobile data computer technology which is now installed on the buses to current “tablet” technology. MDCs are used to communicate customer information for deviations, mapping, messages, and other critical information to the bus operator. 

Project Funding:

Project Funding Amount: No grants have been attached to this project.

$0.00

Update:
   Dispatcher training conducted June 12-16. Minor debugging of voice announcement system continues.  

Last Update: Friday July 28, 2017