Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Lee Sommers

Current Project Status: Design

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL

Project Funding Amount: $80,000.00

Update:
   Burns and McDonnell are currently working with Kusters to verify the arrangement of the conveyor and washer/compactor to determine if they can go out the north wall. We have also requested pricing for equipment and drawings to begin site layout. Burns and McDonnell also met with sky light vendor to determine design requirements for the openings. Burns and McDonnell have created the base drawing sheets. 

Last Update: Tuesday April 25, 2017