Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Lee Sommers

Current Project Status: Design

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL

Project Funding Amount: $80,000.00

Update:
   Burns and McDonnell is currently in the design phase for the installation of one or possible two screens in the pump station. On February 23 they made an onsite visit to the site. 

Last Update: Wednesday March 1, 2017