Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Lee Sommers

Current Project Status: Design

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL

Project Funding Amount: $80,000.00

Update:
   Burns and McDonnell (BM) held a 90% design review on the plans and specifications on May 24, 2017. BM determined that the opinion of probable cost (OPC) which came in lower than expected. The current cost of the Browns Branch Pumpstation is $618,000. In addition, BM who was also designing modification to the Plant Pumpstation, located within the plant proper developed an OPC of $224,000. Both of these costs are lower than the current budget of 1.2 million. It is the City Staffs opinion, along with BM that combining these projects would be more cost effective and with the lower costs additional work could be performed in a single project. BM is currently looking at a second rake and an automatic transfer switch for the future generator at Browns Branch. At the Plant Pumpstation an extension of the conveyor is being investigated so it will empty into the dumpsters instead of the floor of the station. 

Last Update: Thursday June 22, 2017