Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL
   Water Protection Operating Fund

Project Funding Amount: $1,286,650.00

Update:
   Garney has been directed in Change Order 4 to change the electrical service connection from a Delta service to a wye service connection. The wye connection will become the new industrial standard so the change was made to the wye to start the transition toward that goal. Garney indicated that the change will cause a delay in the delivery in the Motor Control Centers delaying the project approximately 28 days. 

Last Update: Tuesday May 29, 2018