Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Bartlett Park's New multi generational playground & disc golf course
 

Project Information

Bartlett Park's New multi generational playground & disc golf course
313-345

Project Manager: David Frazier

Assistant Project Manager: Alan Dewey

Current Project Status: Design

Project Scope:
   This playground equipment will be a new inclusive multigeneratonal playground structure and installation of a disc golf course at Bartlett Park 

Project Funding:
   CIP Sales Tax
   MDNR PARKS GRANT
   Parks Department Fund

Project Funding Amount: $691,500.00

Update:
   Had Pre-Construction Meeting for the restrooms with Herner Construction on 5/21/18.There will be a 6 week lead time for the block. 

Last Update: Wednesday May 23, 2018