Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2017 Urban Trail system Maintenance
 

Project Information

2017 Urban Trail system Maintenance
313-150

Project Manager: Rick Spriggs

Current Project Status: Project Initiation

Project Scope:
   to repair all the concrete cracks on the older Trails throughout the city. 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds

Project Funding Amount: $328,697.00

Update:
   Plans and specs have also have been sent to MoDOT for their comments. Once we can get this project approved through MoDOT we can then proceed to get this project out to bid. 

Last Update: Tuesday June 26, 2018