Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2018 Use Tax Concrete Repair Program
 

Project Information

2018 Use Tax Concrete Repair Program
213-007

Project Manager: Alan Dewey

Assistant Project Manager: Bob Todd

Current Project Status: Construction

Project Scope:
   The total concrete repair for the FY18 fiscal year for the concrete streets in the City of St. Joseph. will be $537,380.00 The city used all the allocated CIP Funds and Use tax funds for FY18. 

Project Funding:
   USE Tax

Project Funding Amount: $497,380.00

Update:
   Construction started on 6/25 with Edmond Street. Edmond Street was completed on 7/2. The work on Messanie Street started on 7/5 and completed on 7/19. On 7/23, Jules Street between 3rd and 4th started. the intersection on 4th and Jules was part of the replacement. The completion of that intersection and Street was completed on 7/26. As of 7/30, K&M Concrete was working on the intersection of 5th & Jules. We are on track to complete Jules Street.  

Last Update: Monday July 30, 2018