Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Runway 17/35 Emergency Repairs
 

Project Information

Runway 17/35 Emergency Repairs
413-175

Project Manager: Abe Forney

Assistant Project Manager: Roxanne Patton

Current Project Status: Construction

Project Scope:
   Emergency Pavement Repairs to Runway 17/35 due to weather related heaving.  

Project Funding:
   FTA Capital Assistance Funds

Project Funding Amount: $21,350.00

Update:
   Emergency repairs were made to the main Runway 17/35 pavement July 5, 2018. Excessive heat caused the concrete to fail. Ideker, Inc. was immediately contacted to remove and replace six (6) concrete panels. Work was completed in five (5) days. Documents being processed with State for a 90/10% cost share for emergency grant. Payment to Contractor has been made for this emergency repair. 

Last Update: Tuesday September 25, 2018